8-28-17 city of fdl weekly construction schedule

Seventh Street from South Main Street to South Park Avenue
Schedule:  May 2017 to November 2017
Description:  The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
August 28th to September 1st:  The paving contractor will pour the remaining sidewalk and carriage walk.  The electrical contractor will also complete the wiring and installing light poles this week.  If weather permits the grading contractor will start to prepare the terrace areas for landscaping in the areas where the walk will have final cure.
Traffic Impacts:  Seventh Street is closed to through traffic.  It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours.
North Military Road from West Follett Street to West Scott Street
Schedule:  May 2017 to November 2017
Description:  The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
August 28th to September 1st:  The utility contractor will continue to install sanitary sewer main from Arndt Street to W. Follett Street.  The second utility crew will finish the sanitary sewer main on W. McWilliams and then possibly start the storm sewer in this intersection.  They will then drop back and start water and sanitary sewer laterals from Scott to McWilliams.
Traffic Impacts: Military Road is closed to through traffic.  It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours.
Fifth Street from South Marr Street to South Park Avenue
Schedule:  May 2017 to November 2017
Description:  The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
August 28th to September 1st:  The grading contract will complete the excavation and grading from Ellis Street to Marr Street.  The electrical contractor will follow behind and start to install conduit beginning at Park Street working to the west.
Traffic Impacts:  Fifth Street is closed to through traffic.  It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours.
Ellis Street from Fourth Street to Eight Street (North Leg)
Schedule:  May 2017 to November 2017
Description:  The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
August 28th to September 1st:  The grading contractor will complete the excavation and grading of Ellis Street at the beginning of the week.  The electrical contractor should start installing the electrical conduit along Ellis before weeks end.
Traffic Impacts: Ellis Street is closed to through traffic.  It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs.  Parking is not permitted on the street during working hours.
 